DAB Decision No. 2006: The
Council of the Southern Mountains, Inc.
Department of Health and Human Services
DEPARTMENTAL APPEALS BOARD
Appellate Division
| SUBJECT: |
The Council of the Southern Mountains, Inc. |
DATE: |
December 21, 2005 |
| |
Docket No. A-05-23 |
|
|
| |
|
|
|
| |
Decision No. 2006 |
|
|
DECISION
The Council of the Southern Mountains (CSM) appealed an October
19, 2004 determination of the Administration for Children and Families (ACF)
to terminate federal funding for CSM's Head Start program under 42 U.S.C. §
9831 et seq. ACF found in reviews conducted in November 2003 and March-April
2004 that CSM had failed to correct numerous deficiencies first identified in
an October 2002 review. In response to CSM's appeal, which also requested a
hearing, ACF filed a motion for summary affirmance.
As explained in detail below, we grant ACF's motion because
CSM has not raised a genuine dispute of material fact requiring an evidentiary
hearing. We base our conclusion on the failure of CSM to raise a genuine dispute
regarding ACF's determination that it was not in compliance with several Head
Start performance standards in nine Head Start classrooms operated by the McDowell
County Board of Education (BOE) under a collaboration agreement with CSM (collaboration
classrooms). In particular, we find that CSM failed to raise a genuine dispute
with respect to ACF's findings that, in each of these classrooms, it failed
to individualize the program to meet each child's needs; use its disabilities
service plan as a working document; observe and assess children on an ongoing
basis; implement its child outcomes plan; have mechanisms in place for regular
communication with staff; maintain files for each child documenting observations
and assessments, individualized plans, and child outcomes data; implement procedures
for ongoing monitoring of classrooms; and provide training to teachers on Head
Start regulations, performance standards and child outcomes. These findings
provide a basis for termination since they establish that CSM had uncorrected
deficiencies in the areas of Early Childhood Development and Health Services
and Program Design and Management. As a result of these deficiencies, children
in the collaboration classrooms, which constituted a significant part of CSM's
Head Start program, were not receiving services tailored to meet their particular
needs as contemplated by the Head Start statute and regulations. The fact that
ACF's initial deficiency findings involved both collaboration and non-collaboration
classrooms and that the alleged deficiencies in the latter were corrected by
the time of the follow-up review is immaterial since CSM received Head Start
funding for the children in all of the classrooms and, thus, was responsible
for complying with Head Start requirements in all of the classrooms.
In granting ACF's motion, we have also
considered all of CSM's other arguments for reversing the termination but find
them without merit.
Legal
Background
Head Start is a national program that
provides comprehensive child development services. 42 U.S.C. § 9831; 57 Fed.
Reg. 46,718 (October 9, 1992). The program serves primarily low-income children,
ages three to five, and their families. id. The Department of Health and Human
Services (HHS), through ACF, awards grants to community-based organizations that
assume responsibility for delivering Head Start services -- including education,
nutrition, health, and social services -- to their communities. id.
To ensure that eligible children and their
families receive high quality services responsive to their needs, Head Start
grantees must comply with the Head Start Program Performance Standards codified
in 45 C.F.R. Part 1304. Head Start Performance Standards (final rule), 61 Fed.
Reg. 57,186 (Nov. 5, 1996). These performance standards cover the entire range
of Head Start services and constitute the minimum requirements that a Head Start
grantee must meet in three areas: Early Childhood Development and Health
Services; Family and Community Partnerships; and Program Design and Management.
HHS is required to conduct a periodic
review of each Head Start grantee at least once every three years. 42 U.S.C. §
9836a(c)(1)(A). If as a result of the review the "responsible HHS official"
finds that a grantee has one or more "deficiencies," the official must "notify
the grantee promptly, in writing, of the finding, identifying the deficiencies
to be corrected and, with respect to each identified deficiency, . . . inform
the grantee that it must correct the deficiency either immediately or pursuant
to a Quality Improvement Plan." 45 C.F.R. § 1304.60(b).
A grantee's noncompliance with a program
performance standard or other Head Start requirement constitutes a "deficiency"
if it meets one of the definitions of that term in 45 C.F.R. § 1304.3(a)(6). The
definitions in sections 1304.3(a)(6)(i) and 1304.3(a)(6)(iii) are relevant here.
Sections 1304.3(a)(6)(i) provides that a deficiency includes:
An area or areas of performance in which
an Early Head Start or Head Start grantee agency is not in compliance with State
or Federal requirements, including but not limited to, the Head Start Act or one
or more of the regulations under parts 1301, 1304, 1305, 1306 or 1308 of [title
45 C.F.R.] and which involves:
C) A failure to perform substantially the
requirements related to Early Childhood Development and Health Services, Family
and Community Partnerships, or Program Design and Management . . . . 1
Section 1304.3(a)(6)(iii) provides that a
deficiency can be "any other violation" of the Head Start Act or regulations
which "the grantee has shown an unwillingness or inability to correct within the
period specified by the responsible HHS official, of which the responsible HHS
official has given the grantee written notice of [sic] pursuant to section
1304.61." Under this provision, a violation of the Head Start Act or regulations
that does not constitute a deficiency under sections 1304.3(a)(6)(i) or (ii) is
deemed to be a deficiency only after the grantee has
demonstrated an inability or unwillingness to correct it within the time frame
specified by the responsible HHS official.
If the responsible HHS official determines
that a grantee has one or more deficiencies as defined in section 1304.3(a)(6)--
he or she will notify the grantee
promptly, in writing, of the finding, identifying the deficiencies to be
corrected and, with respect to each identified deficiency, will inform the
grantee that it must correct the deficiency either immediately or pursuant to a
Quality Improvement Plan.
45 C.F.R. § 1304.60(b). 2
If the responsible HHS official permits
the grantee to correct a deficiency pursuant to a Quality Improvement Plan
(QIP), the grantee must submit a QIP that specifies, for each identified
deficiency, "the actions that the grantee will take to correct the deficiency
and the time frame within which it will be corrected." 45 C.F.R. § 1304.60(c).
The QIP must be approved by the responsible HHS official. See 45 C.F.R. § 1304.60(d). The period for correcting
deficiencies under an approved QIP may not exceed one year from the date the
grantee is notified of them. 42 U.S.C. § 9836A(d)(2)(A); 45 C.F.R. § 1304.60(c).
The requirement that deficiencies be corrected within one year ensures that
families receive the full benefits of the Head Start program and that grantees
have sufficient incentive to take prompt action to improve their programs. Target Area Programs for Child Development, Inc., DAB
No. 1615 (1997).
If a grantee with an approved QIP fails to
correct its deficiencies within the timeframe specified in the QIP, then ACF may
terminate funding. 45 C.F.R. § 1304.60(f); First State
Community Action Agency, DAB No. 1877, at 9 (2003). Section 1303.14(b)(4)
authorizes ACF to terminate funding if a grantee "has failed to timely correct
one or more deficiencies as defined in 45 C.F.R. Part 1304." This is one of nine
grounds for termination set out in section 1303.14(b), which states that
"[f]inancial assistance may be terminated for any or all of [these] reasons."
ACF's October 19, 2004 letter notified CSM that ACF was terminating its grant
based on sections 1303.14(b)(4), (b)(7), and (b)(9). Section 1303.14(b)(7)
authorizes termination if a grantee "has failed to comply with the requirements
of the Head Start Act." Section 1303.14(b)(9) authorizes termination if a
grantee "fails to abide by any other terms and conditions of its [grant] award .
. . or any other applicable laws, regulations, or other applicable Federal or
State requirements or policies."
The responsible HHS official initiates a
termination action by issuing a notice of termination that sets forth, among
other things, the legal basis for termination, the factual findings on which the
termination is based, and citations to appropriate legal authority. 45 C.F.R. §
1303.14(c). The grantee may appeal the termination action to the Board, which is
authorized to conduct a hearing on the matter on behalf of the Secretary. 45
C.F.R. § 1303.14; Mansfield-Richland-Morrow Total
Operation Against Poverty, Inc., DAB No. 1671 (1998). A grantee's appeal
must, among other things: "[s]pecifically identify what factual findings are
disputed"; "identify any legal issues raised, including relevant citations"; and
"include . . . each document the grantee believes is relevant and supportive of
its position." 45 C.F.R. § 1303.14(d)(2)-(4).
In its motion for summary affirmance, ACF
sets forth the standard for granting summary judgment. Summary judgment is
appropriate when there is no genuine dispute as to any material fact, and the
moving party is entitled to judgment as a matter of law. Union Township Community Action Organization, DAB No.
1976, at 6. The party moving for summary judgment bears the initial burden of
showing the basis for its motion and identifying the portions of the record that
it believes demonstrate the absence of a genuine factual dispute. See Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986).
If a moving party carries its initial burden, the non-moving party must "come
forward with 'specific facts showing that there is a genuine issue for trial.'"
Matsushita Elec. Industrial Co. v. Zenith Radio, 475
U.S. 574, 587 (1986) (quoting Fed. R. Civ. P. 56(e)). 3 To defeat an
adequately supported summary judgment motion, the non-moving party may not rely
on general denials in its pleadings or briefs, but must furnish evidence of a
genuine dispute concerning a material fact--a fact
that, if proven, would affect the outcome of the case under governing law. id.
at 586, n.11; Celotex, 477 U.S. at 322. In deciding a
summary judgment motion, a tribunal must view the entire record in the light
most favorable to the non-moving party, drawing all reasonable inferences from
the evidence in that party's favor. Union Township
Community Action Organization.
Factual and
Procedural Background
CSM has provided Head Start services in
McDowell County, West Virginia since 1965. On December 11, 2001, CSM entered
into a "Collaboration Agreement" with the McDowell County Board of Education.
CSM Ex. 74, Att. E. The agreement contains the following description of the
collaboration:
This collaboration is a center-based
wrap-around model, which is located in designated McDowell County School System
elementary school buildings. In this model, the McDowell County School System
will provide early childhood educational services utilizing pre school curricula
with high quality standards. The Council of the Southern Mountains Head Start
will provide necessary early childhood health, family and community
partnerships, disabilities and program design and management services to fully
meet their performance standards for dually enrolled children. The collaboration
model will . . . serve not less than 60 Head Start eligible children and
families. The McDowell County Schools classroom staff will be employees of the
McDowell County Board of Education. All Head Start staff will be employees of
The Council of the Southern Mountains' Head Start Program.
id. at 1. It is not disputed that during
the time period relevant to this appeal, nine of CSM's 23 Head Start classrooms
operated under the collaboration agreement. CSM Ex. 5, at 1. Of the 320 children
CSM was funded to serve, 80 to 87 (25% to 27%) were in collaboration classrooms.
CSM Appeal Br. at 2; CSM Ex. 1, at 2. 4
From October 21 through 25, 2002, ACF
conducted an on-site review of CSM's Head Start program. By letter dated
February 13, 2003, ACF notified CSM that, as a result of this review, it had
determined that CSM had failed to perform substantially the requirements related
to Early Childhood Development and Health Services and the requirements related
to Program Design and Management, as described in the report accompanying the
notice (referred to by ACF as the "2003 Head Start Review Report"). ACF stated
that the "non-compliance items" in these areas "are of such significance that we
have determined that a deficiency exists in your Head Start program as defined
in 45 CFR 1304.3(a)(6)(i)(C)." CSM Ex. 2, at 2 (unnumbered). ACF further stated
that CSM was therefore required to develop a QIP "to correct the deficiencies
that we have identified in this report" and that failure to correct the
deficiencies within 180 days from CSM's receipt of the notice would result in
issuance of a notice of termination. 5 id. at 4 (unnumbered). The 2003 Review Report
identified deficiencies in the areas of Child Development and Health Services
(including Prevention and Early Intervention; Individualization; Disabilities
Services; and Curriculum and Assessment) and Program Design and Management
(including Planning; Communication; Record-keeping and Reporting; Ongoing
Monitoring; Self-Assessment; Human Resources; Fiscal Management; Eligibility,
Recruitment, Selection, Enrollment and Attendance; and Facilities, Materials,
Equipment and Transportation). CSM Ex. 1.CSM submitted a QIP that ACF approved
on July 23, 2003. ACF Br. dated 1/25/05, at 6, citing CSM Ex. 3. 6 ACF conducted a
follow-up on-site review from November 16 through 20, 2003, and from March 29
through April 2, 2004. On July 2, 2004, ACF notified CSM that it was terminating
CSM's Head Start grant. Docket No. A-04-142, CSM Motion to Dismiss or Remand,
dated 8/5/04, Ex. A. ACF enclosed with this notice its report on the follow-up
review (referred to by ACF as the "2004 Head Start Follow-Up Report"). CSM Ex.
1. The 2004 Follow-Up Report found noncompliance in some of the same areas as in
2003: individualization, disabilities services, and curriculum and assessment
under the heading "Child Development and Health Services;" and planning,
communication, record-keeping and reporting, ongoing monitoring, human
resources, and fiscal management under the heading "Program Design and
Management." The 2004 Follow-Up Report found specifically that CSM had failed to
correct its noncompliance in these areas with respect to the collaboration
classrooms.
On August 5, 2004, in response to ACF's
July 2 letter, CSM filed a notice of appeal of the termination and a motion to
dismiss or remand, alleging that the letter did not comply with the notice
requirements in 45 C.F.R. § 1303.14. The Board agreed with some of CSM's
allegations of inadequate notice, and on August 13, 2004, remanded the case to
ACF. Docket No. A-04-142, Ruling on Motion to Dismiss or Remand. 7 ACF issued a
replacement termination notice dated October 19, 2004, enclosing new copies of
both the 2003 Review Report and the 2004 Follow-Up Report. 8 CSM Exs. 5-7. In the
October 19, 2004 notice, ACF notified CSM that it had determined that CSM failed
to correct "nine deficiencies identified in the 2003 Head Start Review Report
within the time period specified in CSM's approved QIP . . . ." CSM Ex. 5, at 3.
ACF stated that "the nine deficiencies that remained uncorrected related to
Individualization, Disabilities Services, Curriculum and Assessment, Planning,
Communication, Record-keeping and Reporting, Ongoing Monitoring, Human Resources
and Fiscal Management, and involved failures to perform substantially the
requirements related to Early Childhood Development and Health Services and
Program Design and Management . . . ." CSM Ex. 5, at 3. ACF further stated that
termination was warranted under 45 C.F.R. §§ 1303.14(b)(4), (b)(7) and (b)(9).
CSM timely filed an appeal with 46
exhibits (including affidavits) and requested additional documents from ACF. ACF
then filed 32 exhibits as well as a motion for summary affirmance (MSA). In
support of this motion, ACF asserts that "no hearing is warranted in this case
because CSM has not presented sufficient evidence that there is any genuine or
material issue of fact with respect to ACF's findings." ACF Br. dated 1/25/05,
at 12. ACF maintains that "numerous deficiencies remained uncorrected at the
time of the follow-up review, which was beyond the 180 day period required for
correction." id. at 7. ACF cites all nine areas of noncompliance identified in
its revised notice of termination. With two exceptions (involving the
requirements for ongoing monitoring of fiscal management in 45 C.F.R. §
1304.51(i)(2) and standards for financial management systems in 45 C.F.R. §
74.21(b)(3)), ACF relies solely on allegations of noncompliance involving the
collaboration classrooms.
With its response to ACF's motion, CSM
submitted Exhibits 47 through 68 and a Motion for Production and Taking of
Additional Discovery, which included a request to take depositions from, or
submit written questions to, the ACF reviewers and ACF's Regional Administrator.
The Presiding Board Member denied the request for depositions or written
questions on the ground that CSM had not shown that this additional discovery
was necessary, and ACF agreed to produce the documents requested by CSM. Letter
to parties dated 4/5/05. After receiving these documents, CSM moved to
supplement the record with proposed Exhibits 69 through 71. The Presiding Board
Member admitted Exhibits 69 and 71 into the record but denied CSM's motion to
admit proposed Exhibit 70 on the ground that CSM failed to establish that it
constituted part of a "draft review report" on the October 2002 on-site review,
as CSM alleged, rather than an individual reviewer's notes, as ACF argued. 9 Letter to parties
dated 5/25/05. The Board subsequently issued an Order to Develop the Record to
which both parties responded.
ANALYSIS
On appeal, CSM says that it disputes ACF's
initial findings of noncompliance, which appear in the 2003 Review Report, in
the following areas: individualization, disabilities services, curriculum and
assessment, communication, human resources, and fiscal management (as well as
facilities and enrollment, as to which ACF found the noncompliance was timely
corrected). 10
See CSM Appeal Br. at 25-26 and Motion to Supplement
the Record at 2-5. CSM also contends that even assuming it was initially out of
compliance in all nine areas, it timely corrected all of the noncompliance. CSM
contends further that any initial noncompliance or failure to timely correct
such noncompliance that was related to the collaboration classrooms was due to
factors beyond its control: the State takeover of the McDowell County school
system as well as major flooding in McDowell County. According to CSM, ACF
should have taken these factors into account in determining whether there were
deficiencies that warranted termination. CSM makes several other arguments for
reversing ACF's decision to terminate its grant.
Below, we first address the individual
findings of noncompliance on which ACF based its determination that CSM had
deficiencies in Early Childhood Development and Health Services and Program
Design and Management. We then explain the basis for our conclusion that CSM has
raised no genuine dispute of material fact regarding these findings. Finally, we
address CSM's other arguments.
I. CSM does not
raise a genuine dispute of material fact as to eight of the nine findings of
noncompliance on which ACF's motion for summary affirmance relies. 11
A. Individual
findings of noncompliance
ACF cited findings in the 2003 Review
Report and the 2004 Follow-Up Report concerning the provisions cited below. It
is important to note that it is undisputed that all nine classrooms or teachers
referred to throughout the 2004 Follow-Up Report were collaboration classrooms
or teachers.
1. Early Childhood
Development and Health Services
a.
Individualization
Section 1304.20 of 45 C.F.R., "Child
health and developmental services," provides:
(b) Screening for developmental, sensory,
and behavioral concerns.
* * * * * (3) Grantee and delegate
agencies must utilize multiple sources of information on all aspects of each
child's development and behavior, including input from family members, teachers,
and other relevant staff who are familiar with the child's typical behavior.
* * * * *(f) Individualization of the
program. (1) Grantee and delegate agencies must use the information from the
screening for developmental, sensory, and behavioral concerns, the ongoing
observations, medical and dental evaluations and treatments, and insights from
the child's parents to help staff and parents determine how the program can best
respond to each child's individual characteristics, strengths and needs.
In the 2003 Review Report, ACF found that
CSM "only uses the Denver Prescreening Developmental Questionnaire II to plan
for individualization. This screening process is incomplete and does not meet
the Performance Standards, which require that the grantee use multiple sources
of data to plan for individualization." CSM Ex. 1, at 4.
In the 2004 Follow-Up Report, ACF found
that this noncompliance had not been corrected. ACF stated that "[a]
developmental screening instrument was not utilized to individualize for
children in all of the classrooms, nor had individualization for children been
documented." More specifically, ACF stated that lesson plans in nine classrooms
did not contain documentation of individualization, that teachers in those
classrooms confirmed in interviews that there was no method of
individualization, and that there was no parental input into planning for
children's goals to assure individualization, as evidenced in part by the
absence of documentation that teachers conducted home visits with parents. CSM
Ex. 6, at 3.
b. Disabilities
Services
Section 1308.4(d) of 45 C.F.R. is part of
the Head Start Performance Standards on Services for Children with Disabilities,
while Part 1304 specifically governs the area of Early Childhood Development and
Health Services. A violation of a Head Start requirement that does not appear in
the regulations specifically pertaining to any of three broad areas of
performance listed in section 1304.3(a)(6)(i)(C) (including Early Childhood
Development and Health Services) may nevertheless constitute a deficiency as
defined in that section if the violation "is related to a failure [to] perform
substantially requirements related to" one of these three broad areas of
performance. Saginaw County Community Action Committee,
Inc., DAB No. 1953, at 50 (2004). CSM does not dispute that the alleged
disabilities service plan violation involves a failure to perform requirements
related to Early Childhood Development and Health Services. The specific
provisions of section 1308.4(d) on which ACF relied are captioned "Purpose and
scope of disabilities service plan."
(d) The Head Start grantee and delegate
agency must use the disabilities service plan as a working document which guides
all aspects of the agency's effort to serve children with disabilities. This
plan must take into account the needs of the children for small group
activities, for modifications of large group activities and for any individual
special help.
In the 2003 Review Report, ACF found that
CSM did not use the disabilities service plan as a working document, as
evidenced by the fact that staff interviewed were unsure of the process for
providing disability services, lesson plans and classroom materials did not
reflect provisions for children with special needs, and there was no
documentation showing how the disabilities service plan was used throughout the
program. CSM Ex. 1, at 4-5. In the 2004 Follow-Up Report, ACF found that CSM had
not corrected this noncompliance. The report states that nine teachers who were
interviewed had not been provided with a copy of the disabilities services plan
and had no knowledge of the existence or content of the plan. According to the
report, CSM's Head Start Director agreed that the disabilities plan could not be
utilized as a working document in the nine classrooms since the teachers did not
have a copy of the plan. CSM Ex. 6, at 4. The report also states that these nine
teachers did not attend pre-service training on the disabilities service plan
and that CSM did not schedule any additional disabilities training with these
teachers. id. at 3.
c. Curriculum and
Assessment
Section 1304.21 of 45 C.F.R., "Education
and early childhood development," provides:
(c) Child
development and education and approach for preschoolers.
* * * * * *(2) Staff must use a variety of
strategies to promote and support children's learning and developmental progress
based on the observations and ongoing assessment of each child (see 45 CFR
1304.20(b), 1304.20(d), and 1304.20(e)).
In the 2003 Review Report, ACF found that
CSM did not individualize the curriculum it had selected (the Creative
Curriculum) or adapt the environment to promote and support the children's
learning by providing individualized appropriate activities. In addition, ACF
found that goals were not established for each child based on assessments, that
each child's progress was not recorded, and that there was "no documentation
that demonstrates linkage of observation to individualized, planned activities .
. . ." CSM Ex. 1, at 6-7. In the 2004 Follow-Up Report, ACF found that CSM had
not corrected this noncompliance. The report states that nine classrooms did not
have a method for observing and assessing children. It further states that the
teachers in these classrooms "did not differentiate in providing strategies for
children's learning according to their individual needs." According to the
report, these teachers "reported that they retained each child's developmental
level in memory," and the supplemental curriculum they used "consisted of
pre-packaged materials used with every child without any determination of
whether the goals matched the skill level of each child." CSM Ex. 6, at 7.
2. Program Design
and Managementa. PlanningSection 1304.51 of 45 C.F.R., "Management systems
and procedures," provides:
(a) Program
planning. (1) Grantee and delegate agencies must develop and implement a
systematic, ongoing process of program planning that includes consultation with
the program's governing body, policy groups, and program staff, and with other
community organizations that serve Early Head Start and Head Start or other
low-income families with young children. Program planning must include:
* * * * *(iii) The development of written
plan(s) for implementing services in each of the program areas covered by this
part (e.g., Early Childhood Development and Health Services, Family and
Community Partnerships, and Program Design and Management). (See the
requirements of 45 CFR Parts 1305, 1306 and 1308.)
In the 2003 Review Report, ACF found that
CSM's planning process did not reflect an analysis of child outcomes data, was
not ongoing, and did not address children's developmental progress. CSM Ex. 1,
at 10-11.
In the 2004 Follow-Up Report, ACF found
that CSM had not corrected this noncompliance. The report states that although a
written plan for using child outcomes data for future planning had been
developed, it was not implemented in nine classrooms. According to the report,
the nine teachers indicated in interviews that they did not know about the
"Child Outcomes requirement." 12 CSM Ex. 6, at 9-10.
b.
Communication
Section 1304.51, "Management systems and
procedures," provides:
(e) Communication
among staff. Grantee and delegate agencies must have mechanisms for regular
communication among all program staff to facilitate quality outcomes for
children and families.
In the 2003 Review Report, ACF found that
program policies and procedures did not exist for regular communication among
staff. The report specifically states that "[t]here is no system to communicate
changes in enrollment, tracking information, or follow-up procedures. Also,
there is no system for communication with the Pre-K collaboration classrooms."
The report notes that CSM uses a communication log, but states that the logs
reviewed were incomplete and gave little information about the area of the
program being supervised. CSM Ex. 1, at 11.
In the 2004 Follow-Up Report, ACF found
that CSM had not corrected this noncompliance. The report states that
"communication was a serious obstacle in the collaboration" between CSM and the
county school system. The report noted that the McDowell County School District
Assistant Superintendent, the Title I Director, and the Title I Parent Educator
stated in interviews that the results from the initial on-site review were not
shared with them, that they were unaware of and not involved in the development
of the QIP, and that there was little communication regarding training or
orientation about Head Start requirements. The report also states that
interviews with the nine collaboration classroom teachers "revealed that there
was inadequate communication with the Head Start Program" since none of them
expressed any knowledge of the child outcome measures, seven of them were
unaware of the role of the Family Support Advocates in working with families,
and all nine stated that they did not receive any feedback from the Head Start
Education Managers who visited their classrooms. CSM Ex. 6, at 10-11.
c.
Record-keeping
Section 1304.51, "Management systems and
procedures," provides:
(g) Record-keeping
systems. Grantee and delegate agencies must establish and maintain
efficient and effective record-keeping systems to provide accurate and timely
information regarding children, families, and staff and must ensure appropriate
confidentiality of this information.
The 2003 Review Report states:
Review of program-wide records reveals
that there is not a system in place which will provide efficient and effective
record keeping information in order to monitor and assure quality program
services. Files lack consistency, accuracy, and in some cases are
incomplete.
CSM Ex. 1, at 11.
In the 2004 Follow-Up Report, ACF found
that CSM had not corrected this noncompliance. ACF found specifically that 29
children's files in nine classrooms did not contain on-going observations, child
assessments, individualized plans or child outcomes data, and that interviews
with the nine teachers validated that this information was not in the children's
files. ACF Ex. 6, at 11.
d. Ongoing
Monitoring Section 1304.51, "Management systems and procedures," provides:
(i) Program
self-assessment and monitoring.
* * * * *(2) Grantees must establish and
implement procedures for the ongoing monitoring of their own Early Head Start
and Head Start operations, as well as those of each of their delegate agencies,
to ensure that these operations effectively implement Federal regulations. In
the 2003 Review Report, ACF found, based on record reviews, interviews with
staff, and observations by reviewers, "that monitoring of overall program
operations is not tied to Performance Standards and is not well established or
implemented in a systematic manner." The report states that monitoring was
"infrequent" and monitoring reports were "vague and incomplete." CSM Ex. 1, at
11.
In the 2004 Follow-Up Report, ACF found
that the noncompliance with section 1304.51(i)(2) had not been corrected. The
report states that nine classrooms were not monitored for individualization,
screening, assessments, or curriculum implementation. The report further states
that a review of the monitoring schedule showed that six classrooms had been
visited only once and three had been visited only twice during the entire school
year, and that all nine teachers reported that they received no feedback from
monitoring. The report also finds that "[t]here was a lack of adequate
monitoring in the area of fiscal management as evidenced by continuing year end
balances, over $1,200 in bank overdraft charges last year, and the lack of
proper contract administration of the collaborative partnership." CSM Ex. 6, at
12.
e. Human
Resources
Section 1304.52, "Human resources
management," provides:
(k) Training and
development.
* * * * *(2) Grantee and delegate agencies
must establish and implement a structured approach to staff training and
development, attaching academic credit whenever possible. This system should be
designed to help build relationships among staff and to assist staff in
acquiring or increasing the knowledge and skills needed to fulfill their job
responsibilities, in accordance with the requirements of 45 CFR 1306.23. 13
In the 2003 Review Report, ACF found that
no staff development plans were maintained for Head Start program staff to help
them acquire increased knowledge and skills to fulfill their job
responsibilities. In particular, the report states that CSM had not developed a
plan to train the BOE staff on Head Start performance standards and that
disabilities training had not been provided to staff. CSM Ex. 1, at 14.
In the 2004 Follow-Up Report, ACF found
that CSM had not corrected this noncompliance. The report states that nine
teachers had not received training in Head Start regulations, performance
standards, or child outcome requirements. This finding was based on interviews
with the nine teachers and the Head Start Director, as well as on the absence of
documentation in any of the training records to demonstrate that these teachers
attended training on any of these topics. CSM Ex. 6, at 16.
B. CSM's failure to
raise any genuine dispute of material fact
In its appeal brief, CSM states that ACF's
findings in the 2004 Follow-Up Report that it failed to correct the deficiencies
identified above were wrong. In addition, CSM challenges the findings in the
2003 Review Report regarding individualization, curriculum and assessment,
planning, communication, and human resources.
CSM submitted numerous exhibits (including
affidavits) with its appeal brief to support its position that it corrected its
alleged initial noncompliance with these requirements and, where applicable,
that it was in compliance with these requirements at the time of the initial
on-site review. See CSM Appeal Br. at 38, citing CSM
Exs. 21, 22, 26, 27, and 45 (individualization); id.
at 39-40, citing CSM Exs. 28, 29, 31-33, 36, and 46 (at 103-114) (disabilities);
id. at 40-41, citing CSM Exs. 37 and 38 (curriculum
and assessment); id. at 43, citing CSM Ex. 45
(planning); id. at 44, citing CSM Ex. 46, at 140-141 (communication); id. at 45, citing CSM Ex. 46, at 141-142
(record-keeping); id. at 46, citing CSM Ex. 39 and
CSM Ex. 46, at 144-145 (ongoing monitoring); and id.
at 47, citing CSM Exs. 40 and 41 (human resources).
In its motion for summary affirmance, ACF
argued that none of the exhibits submitted by CSM "contradict[s]" the findings
in the 2004 Follow-Up Report because the exhibits do not pertain to the nine
collaboration classrooms or teachers. In particular, ACF asserted that CSM's
exhibits do not address the findings that: 1) individualization did not occur in
the collaboration classrooms, 2) the collaboration classroom teachers had not
received a copy of the disabilities service plan or received training on using
the plan, 3) the collaboration classroom teachers used a supplemental curriculum
without observing and assessing children to determine whether the curriculum was
matched to the skill level of each child, 4) the child outcomes plan was not
implemented in the collaboration classrooms, 5) the communication system did not
provide for direct communication with staff in the collaboration classrooms, 6)
the children's files in the collaboration classrooms were incomplete, 7) there
was no ongoing monitoring of the collaboration classrooms, 14 and 8) the
collaboration classroom teachers did not receive any training with respect to
Head Start performance standards, regulations, or child outcomes. MSA at 23, 26,
31, 34, 36-37, 39, 43, and 44-45.
In response to ACF's motion, CSM
maintained that it corrected any noncompliance with the requirements in
question. CSM submitted several additional exhibits in support of its position.
See CSM Response to MSA at 36-37, citing CSM Exs.
47-50, 62-65 (individualization); id. at 37, citing
CSM Exs. 66, 67 (disabilities); id. at 39, citing Exs. 47-50, 56, and 63-65
(curriculum and assessment); id. at 42, citing CSM
Exs. 63-65 (each at 9), and CSM Ex. 67, 23 (planning) 15; id. at 44-45, citing CSM Exs. 52, 53, 57, and 67
(communication); id. at 47-48, citing CSM Exs. 60, 67
(record-keeping); id. at 49-50, citing CSM Exs. 51,
58, 60, 63-65, 67, and ACF Ex. 19 (ongoing monitoring); and id. at 51, citing CSM Exs. 61 and 67 (human resources).
16 However, CSM did
not specifically argue that any of the documentation it had submitted showed
that it complied with the applicable requirements in any of the nine
collaboration classrooms. In addition, none of the additional affidavits
submitted by CSM specifically alleged that CSM had complied with the applicable
requirements in any of the nine collaboration classrooms.
CSM also argued that the previously
submitted affidavit of its Disabilities Manager directly contradicted ACF's
findings. However, the Disabilities Manager alleges that "[s]everal training
sessions have occurred," not that the collaboration classroom teachers received
training. CSM Ex. 66, 4. In addition, the Disabilities Manager's allegation that
"all staff members have been provided copies of the disabilities plan" does not
on its face encompass the collaboration classroom teachers, since they were
employed by the county schools rather than CSM's Head Start Program and,
therefore, are not "staff" of CSM. CSM Ex. 74, Att. E at 1. Since there is no
clear reference to the collaboration classrooms in this affidavit, we would have
been hard pressed to conclude at any point in this proceeding that these
statements (or any similarly general statements in other affidavits regarding
this or other allegedly uncorrected deficiencies) raise a genuine dispute of material fact, even when viewed most favorably to CSM.
However, even assuming we could reasonably have reached that conclusion at some
point in this proceeding, we cannot do so after the issuance of the Board's
Order to Develop the Record and CSM's response to it, both of which are
discussed below.
After reviewing the record, the Presiding
Board Member notified the parties that she found no indication that any of the
teachers identified in CSM's affidavits or other exhibits submitted with respect
to any of the alleged deficiencies were teachers in collaboration classrooms.
She also noted that none of the classrooms identified in CSM's exhibits appeared
to be collaboration classrooms. 17 The Presiding Board Member therefore directed
CSM as follows:
CSM . . . should state . . . whether or
not it disputes that none of the teachers identified in the exhibits on which it
relies taught in BOE [collaboration] classrooms during the relevant time
periods. If CSM contends that certain of these teachers did teach in the BOE
classrooms during the relevant time periods, CSM should make a proffer of
evidence to support its position with respect to each teacher. At minimum, the
proffer should identify the teacher and the BOE classroom in which he/she taught
as well as the time period during which he/she taught there. CSM should also
state whether or not it disputes that none of the classrooms for which it
provided documents were BOE classrooms. If CSM alleges that certain documents it
submitted as exhibits do relate to certain BOE classrooms, it should make a
proffer of evidence to support its allegation. This proffer, at minimum, should
identify each document that relates to a BOE classroom and the classroom to
which it relates
Order to Develop the Record dated 6/20/05,
at 2.
In response to the Board's Order, CSM
proffered the affidavit of its Head Start Director, Pamela Waddell. CSM Response
to Order to Develop the Record at 2, citing CSM Ex. 73. Ms. Waddell states that
she is the person who "pulled from [CSM's] . . . records examples of lesson
plans and individualization to be submitted on behalf of [CSM]" and that "[m]ost
of these documents are contained in [CSM's] Exhibits 47, 48, 49 and 50." She
then admits that "[t]he documents do not include examples from the Board of
Education collaborative classrooms." id. at 7. However, Ms. Waddell alleges that
the examples of monitoring reports submitted as CSM Exhibit 39 include
monitoring reports for five collaboration classrooms. CSM Ex. 73, 9.
Five of the six monitoring reports in CSM
Exhibit 39 pertain to collaboration classrooms; nevertheless, this exhibit does
not raise a genuine dispute of material fact with respect to ACF's finding that
CSM failed to timely correct the deficiencies found in the 2003 Review Report.
All of the observations discussed in the monitoring reports were made after
August 26, 2003, the end of the period for correction in CSM's approved QIP.
Thus, these observations could not establish that CSM timely corrected any
noncompliance. 18 In addition, these reports do not specifically
address whether CSM met any of the requirements as to which ACF found it was out
of compliance except monitoring. Even assuming the monitoring reports raised a
factual dispute regarding ACF's finding on monitoring or any of ACF's other
findings, however, CSM submitted no evidence purporting to dispute any of ACF's
findings for the four collaboration classrooms for which there were no
monitoring reports.
CSM also asserts in its response to the
Board's order that some of the documents it submitted earlier (CSM Exhibits
47-50) raise genuine disputes of material fact that preclude summary judgment
for ACF even though CSM acknowledges that these documents address ACF's initial
findings of noncompliance with respect to only non-collaboration classrooms.
According to CSM, since the findings resulting from ACF's initial on-site review
were "based not just on the [BOE] collaborative classrooms," a showing by CSM
that it met the applicable requirements in the non-collaboration classrooms at
the time of this review would preclude ACF from terminating based on
deficiencies found in the follow-up review to be uncorrected only in the
collaboration classrooms. CSM Response to Board Order to Develop the Record at
1-2. 19 If CSM is arguing that it had no deficiency at
the time of the initial review because it met the relevant performance standards
for some of the classrooms in its Head Start program, the argument has no merit.
Since all of the classrooms were subject to the Head Start program requirements,
a deficiency finding on either review could properly be based on noncompliance
in any of the classrooms.
We therefore conclude that the findings of
noncompliance discussed above, either individually or together with the other
findings in the same area, support findings of deficiencies in Early Childhood
Development and Health Services and Program Design and Management.
II. ACF gave
adequate notice of the deficiencies on which the termination was based.
CSM takes the position that ACF's February
13, 2003 letter asserted a single deficiency under 45 C.F.R. §
2304.3(a)(6)(i)(C) that was based on the "theory" that items of noncompliance
constituted a deficiency only when considered collectively. CSM Appeal Br. at
26-27. CSM identifies numerous findings of noncompliance in the 2003 Review
Report that it considers erroneous. See, e.g. id. at
22-28. Applying the aggregation theory it attributes to ACF, CSM then argues
that if even one of the findings is wrong, the deficiency would no longer exist
on the first review and, therefore, could not provide a basis for termination if
found on the follow-up review, since 45 C.F.R. § 1304.60(b) requires ACF to give
CSM notice and an opportunity to correct a deficiency.
CSM's arguments have no merit.
Notwithstanding ACF's statement in the February 13, 2003 letter that "a deficiency exists in your Head Start program as
defined in 45 CFR 1304.3(a)(6)(i)(C)," the notice elsewhere indicates that ACF
found a failure to perform substantially the requirements related to both Early
Childhood Development and Health Services and Program Design and Management. See
CSM Ex. 2 (emphasis added). Under section 1304.3(a)(6)(i)(C), these constitute
separate deficiencies. But even assuming ACF's use of the language "a deficiency
... as defined in 45 C.F.R. § 1304.3(a)(6)(i)(C)" refers to a single deficiency,
this does not suggest a "theory" that every item of noncompliance ACF mentioned
was a necessary element of this deficiency and that ACF could not terminate
after the follow-up review unless all of the noncompliance remained uncorrected.
A deficiency within the meaning of section 1304.3(a)(6)(i)(C) exists where a
grantee fails "to perform substantially the
requirements related to Early Childhood Development and Health Services, Family
and Community Partnerships, or Program Design and Management." (Emphasis added.)
ACF could properly determine that a deficiency existed based on even one finding
of noncompliance if it concluded that the grantee failed to perform
substantially the requirements related to Early Childhood Development and Health
Services or Program Design and Management (the areas of section
1304.3(a)(6)(i)(C) at issue here). 20 As we have discussed, there is no genuine
dispute of material fact regarding eight of the nine findings of noncompliance
on which ACF ultimately proposed to terminate CSM's grant.
CSM also argues that ACF's February 2003
letter did not provide adequate notice because the letter "did not provide many
details regarding the specific items considered in the area of Early Child
Development and Health Services or in the area of Program Design and
Management." CSM Appeal Br. at 15. According to CSM, the February 2003 letter
was unclear "regarding the exact basis for ACF's allegations" of noncompliance
regarding disabilities services, fiscal management, and human resources. 21 id. at 15-16.
22 Even assuming this is true, the regulations at
45 C.F.R. § 1303.14(c)(1) provide that a notice of termination may refer to
specific findings in another document that form the basis for the termination.
As indicated above, the February 2003 letter referred to "deficiencies
identified in" the 2003 Review Report, which contained additional detail. CSM
does not contend that the detail in the 2003 Review Report was insufficient to
give it adequate notice of these deficiencies.
CSM argues further that ACF's February
2003 letter did not give CSM any notice of two deficiencies identified in ACF's
October 19, 2004 termination letter: Planning and Record-keeping. CSM states
that "neither issue was cited" or "mentioned" in the February 13 letter. CSM
Appeal Br. at 17. CSM acknowledges that these two "issues are noted" in the 2003
Review Report, but asserts that "not every item of noncompliance" mentioned in
the report "contributes to a deficiency." id., citing 45 C.F.R. § 1304.61 and The Human Development Corporation of Metropolitan St.
Louis, DAB No. 1703 (1999).
This argument is not persuasive. The 2003
Review Report includes "Planning" and "Record-keeping and Reporting" along with
its other findings under the heading "Program Design and Management." CSM Ex. 1,
at 9-11. As indicated above, ACF's February 13 letter incorporated by reference
the findings in the 2003 Review Report. CSM also addressed Planning and
Record-keeping and Reporting in its QIP. CSM Ex. 3, at 4, 7. Thus, CSM clearly
understood the February 2003 letter as giving notice that problems in these
areas were part of the basis for the finding of a deficiency within the meaning
of section 1304.3(a)(6)(i)(C), which includes a failure to perform substantially
the requirements relating to Program Design and Management. Furthermore, while
CSM is correct that under section 1304.61, certain types of noncompliance do not
constitute a deficiency until after the grantee has been given an opportunity to
correct them (see Human Development Corp. at 8), this
is not true of ACF's findings here that CSM failed to comply with the
requirements for planning and record-keeping. Since ACF cited these findings
under the umbrella requirement Program Design and Management, noncompliance with
these requirements can support an initial deficiency finding under section
1304.3(a)(6)(i)(C) without any prior opportunity for correction.
CSM also points out that the 2003 Review
Report speaks merely of "findings that require corrective action" when
addressing the planning requirement in contrast to "substantial findings that require corrective action"
when addressing the record-keeping requirement. CSM Appeal Br. at 17, citing CSM
Ex. 1, at 10 (emphasis added). 23 CSM suggests that by omitting the word
"substantial," ACF indicated that it did not view the planning findings as
contributing to its determination of a deficiency in Program Design and
Management under section 1304.3(a)(6)(i)(C). We see no basis for this reading.
After quoting the requirement for "development of written plan(s) for
implementing services in each of the program areas covered by this part [e.g.,
Program Design and Management]," the 2003 Review Report explains that CSM did
not meet this requirement because its planning did not use child outcomes data
to guide programmatic decisions. CSM Ex. 1, at 11. Thus, the report makes it
clear that ACF viewed the planning findings, no less than the record-keeping
findings, as contributing to the Program Design and Management deficiency cited
under section 1304.3(a)(6)(i)(C). Moreover, as noted above, by including these
areas in its QIP, CSM indicated that it understood them to be a basis for ACF's
deficiency finding.
CSM's argument also erroneously assumes
that ACF must describe as "substantial" the noncompliance it finds with respect
to each component of the umbrella requirement Program Design and Management in
order to find a "failure to perform substantially the requirements related to .
. . Program Design and Management." The quoted phrase does not necessarily refer
to each of the components, but can refer to performance of those components in
the aggregate. Thus viewed, it is irrelevant whether ACF uses the word
"substantial" when describing the findings related to the individual components
so long as the aggregate findings constitute a "failure to perform
substantially" the requirements related to Program Design and Management.
Finally, CSM argues that it did not
receive adequate notice of the deficiencies because ACF's initial notice "was
not 'prompt' within the meaning of section 1304.60(b)." CSM Appeal Br. at 14.
CSM asserts (and ACF does not dispute) that ACF's 2004 Guide for conducting
on-site reviews states that "delivery of the final Head Start Review Report
within 45 calendar days of the end of the on-site phase of the review is
imperative." id., quoting 2004 PRISM Guide, at 33, n.2. 24 ACF's initial
on-site review was conducted October 21-25, 2002, more than three months before
the February 13, 2003 notice transmitted the 2003 Review Report to CSM. CSM
acknowledges, however, that the 2004 PRISM Guide "was not binding on the ACF
during the 2003 program year . . . ." CSM Appeal Br. at 14. Moreover, even if
the February 13, 2003 notice of the deficiencies was not prompt, CSM does not
cite any authority for invalidating the notice on this ground and does not
allege that it was prejudiced by any delay in issuing the notice. 25
III. ACF could
reasonably require that CSM come into full compliance in order to correct
deficiencies under 45 C.F.R. § 1304.3(a)(6)(i)(C).
CSM argues that termination was not
warranted based on failure to correct a deficiency within the meaning of section
1304.3(a)(6)(i)(C) because CSM "was at least substantially performing the
requirements related to" the requirements for Early Childhood Development and
Health Services and Program Design and Management at the time of the follow-up
review conducted March 29 - April 2, 2004. 26 CSM Appeal Br.
at 31. CSM asserts that ACF erroneously applied a full performance standard in
determining whether CSM had corrected the deficiencies found in the initial
on-site review. In support of its position, CSM cites the definition of a
deficiency under section 1304.3(a)(6)(i)(C) as a "failure to perform
substantially the requirements related" to any of the three areas listed, as
well as the provision in section 1304.3(a)(14) defining the term "[m]inimum
requirements" as meaning "that each . . . Head Start grantee must demonstrate a
level of compliance . . . such that no deficiency, as defined in this part,
exists in its program." CSM reasons that, in order to correct a deficiency, it
need do no more than attain the level of performance at which no deficiency
would have existed in the first instance. CSM also argues that the Board held in
First State Community Action Agency that the
applicable standard is substantial compliance or performance. See CSM Appeal Br. at 29-31; CSM Response to MSA at
27-33.
In First State,
the Board did not decide what constitutes the proper standard but simply
declined to rely on the full compliance standard because it questioned whether
ACF had given the grantee in that case adequate and timely notice of that
standard. Because of the notice issue, the Board looked at whether the grantee
had timely made improvements sufficient to conclude that it was substantially
performing each requirement at issue. See First State at 13, 15.
27 In a later
decision where there was no notice issue, the Board found that ACF could
reasonably apply a full compliance standard. Addressing the same arguments
raised by CSM here, the Board stated:
While the definition of a deficiency sets
forth substantial performance as the applicable standard for an initial finding
of a deficiency in the listed areas, that definition does not address the
standard for correction of an identified deficiency in any area that is set
forth as a basis for termination. Specifically, the provision at 45 C.F.R. §
1304.60(f) that requires correction of identified deficiencies does not
incorporate a substantial performance standard; nor is there any mention of
substantial performance in the termination provision for failure to timely
correct deficiencies at 45 C.F.R. § 1303.14(b)(4). Furthermore, ACF explained a
reasonable basis for the interpretation that correction requires full
compliance; to permit grantees to only partially correct a deficiency to avoid
termination would effectively result in grantees never fully complying with Head
Start requirements. . . .
In addition, PHA does not dispute that,
under section 1304.3(a)(iii) and 1304.61, ACF may require a grantee to come into
full compliance in order to correct noncompliance that does not constitute a
deficiency unless uncorrected. It is logical to read the regulations to accord
ACF the same authority to require full compliance to correct a deficiency, which
represents a significant failing, that is available for uncorrected
noncompliance.
Philadelphia
Housing Authority, DAB No. 1977, at 10-11 (2005); accord DOP Consolidated Human
Services Agency, DAB No. 1689, at 8-9 (1999). 28 Thus, ACF
could properly terminate CSM's Head Start grant if CSM failed to fully correct
any deficiencies found in ACF's initial on-site review. 29.
IV. CSM's
allegation of bias on the part of ACF does not raise a genuine dispute of
material fact.
CSM alleges that "personal animosity" on
the part of ACF reviewers and program officials influenced ACF's findings and
ACF's decision to terminate the grant. According to CSM, "[t]his question of
improper motive renders summary disposition inappropriate." CSM Response to MSA
at 10.
CSM submitted five affidavits alleging
that ACF acted out of bias in making its findings of noncompliance. See CSM Response to MSA at 55-57, citing CSM Ex. 58
(Nuckols affidavit), CSM Ex. 67 (Johnson affidavit), CSM Ex. 59 (Moore
affidavit), CSM Ex. 60 (Melnik affidavit), and CSM Ex. 61 (O'Neal affidavit). As
evidence of bias, the affiants point mostly to alleged disparaging comments by
ACF personnel as well as ACF's questioning whether Head Start funds were used to
pay for a luxury vehicle driven by CSM's former executive director. However, CSM
does not allege any relationship between the alleged comments and particular
findings of noncompliance, and the alleged questioning about possible misuse of
Head Start funds did not result in a finding that became a basis for the
termination. Moreover, questions about the use of Head Start funds do not
evidence bias since reviewers have an obligation to raise such questions.
The O'Neal affidavit does allege that at
the follow-up review, ACF's Human Resources reviewer "did not seem interested in
actually reviewing the changes that the Council had made" and that the reviewer
stated during the March-April 2004 review that she did not need to review
anything other than a training log. Ms. O'Neal concludes, "Because of the
perfunctory nature of the review, I do not believe that the Human Resources
findings were accurate." CSM Ex. 61, 10, 12. Ms. O'Neal does not specifically
allege that the reviewer was biased, however. 30 Even if ACF failed
to conduct a complete review to determine whether CSM's noncompliance with
respect to human resources had been corrected, this would not preclude summary
judgment since CSM did not provide documents on appeal which might raise a
genuine dispute of material fact with respect to ACF's finding that the
noncompliance had not been corrected.
Furthermore, as the Board has previously
stated, "reviewer bias does not affect the reliability of objective evidence,
i.e., evidence that is not dependent on subjective reviewer observation." Philadelphia Housing Authority at 12. As our earlier
discussion indicates, there is no genuine dispute of material fact regarding the
objective evidence supporting the deficiency findings gathered during the
reviews, much of which consists of CSM's own documents, admissions or, in some
cases, absence of documentation. Accordingly, CSM's allegations of bias do not
raise a genuine dispute of material fact that would make summary judgment
inappropriate.
V. CSM has not
raised a genuine dispute as to whether the factors it asserts were beyond its
control caused its noncompliance. CSM asserts that even if it was not in
compliance, factors beyond its control (flooding and the State takeover of the
county school system) caused that noncompliance and ACF should have taken these
factors into consideration. CSM Appeal Br. at 9; see
also CSM Response to MSA, at 12-13. We note at the outset that CSM has not
pointed to any evidence in the record that ACF actually did not give these
factors any consideration. While ACF denies any legal duty to consider such
factors and vigorously disputes that the flooding and State takeover excuse
CSM's noncompliance, it does not actually state that ACF did not consider these
factors. Thus, the record before us does not preclude the possibility that ACF
considered the factors as part of its review process but determined that they
did not excuse CSM's noncompliance. 31
But even if ACF did not consider the
flooding and State takeover, we cannot, after a careful examination of CSM's
argument and the record, find any evidence that could lead a reasonable trier of
fact to conclude, drawing all inferences favorable to CSM, that these factors
caused CSM's noncompliance on either the initial or follow-up review. CSM
presents the following facts. Based on the results of an "Education Performance
Audit of the McDowell County School System," the West Virginia Board of
Education voted on November 8, 2001 to take control of the county school system,
effective immediately. CSM Response to Order to Develop the Record at 6, citing
CSM Ex. 72 (affidavit of Dr. Clifton Moore, CSM's former Executive Director), at
9 and Att. B at 6-8. 32 Approximately one month later, on December 11,
2001, CSM entered into the collaboration agreement with the county school
system. 33 In an affidavit, CSM's Office Manager, Marlene
Valentine, describes the situation that ensued as follows:
Although the agreement was made in
December and efforts to enroll children started immediately, because of the
condition of the local schools just before the take over and the change in
school management, the partnership was not really ready to start up until
February. The two programs had only a short time to work together in the spring
of 2002 due to the fact that in May of 2002 the county experienced another flood
that closed the schools and Head Start.
CSM Ex. 74, 8. Thus, according to Ms.
Valentine, when the review team came in October 2002, "the Head Start Program
was still setting up the collaboration and recovering from the floods." 34 id., 9. Ms. Valentine further states that even
prior to the State takeover, the county school system was "not keeping proper
records," and that "the flooding in May of 2002 either destroyed or delayed
records from the Board of Education. Thus, certain information, such as
attendance and lesson plans for the collaboration classrooms was not available
when the reviewers came in October of 2002." id., 10. Ms. Valentine also alleges
that because of "the many new policies and procedures that had to be put in
place to fix" the county school system's own problems, "[s]cheduling meetings,
training, and monitoring [was] difficult because of conflicts" with the county
school system's "own conferences and training requirements." id., 11. In
addition, according to Ms. Valentine, "because of all the other changes
happening, the Board of Education did not immediately adopt the Creative
Curriculum used by the Head Start Program." id.; see
also CSM Ex. 72 (Moore affidavit), 12, 13, 17; CSM Ex. 73 (Affidavit of
Pamela Waddell, CSM's Head Start Director as of October 2003), 10, 11. Dr.
Moore's affidavit also alleges that-
the conflicts in terms of scheduling, the
priority given to implementation of basic state educational requirements, and
delays in implementation of a uniform curriculum also had detrimental effects on
communication, record-keeping, and monitoring. For example the Council and the
[Head Start Program] communicated program requirements to the BOE, but given the
transformation occurring within the BOE following the state take over and the
absence of general accountability and oversight immediately preceding the take
over, there were misunderstandings and miscommunications. Monitoring efforts
were also made more difficult by uncertain schedules for BOE staff and use of
different curricula.
CSM Ex. 72, 17.E. Dr. Moore also alleges
that a July 2001 flood "contributed to the problems confronting the county's
schools . . . ." id., 11.
Assuming these allegations are true, we
must still conclude that a rational trier of fact could not conclude that CSM's
noncompliance with any of the Head Start program requirements was due to factors
beyond CSM's control. Even viewing the evidence in the light most favorable to
CSM, the evidence is insufficient to show a nexus between the State takeover and
any of the specific findings of noncompliance. As the affidavits acknowledge,
the problems in the county schools that CSM claims caused its initial
noncompliance existed prior to, as well as after, the State takeover. Thus, CSM
entered into the collaboration agreement knowing of the alleged problems. Even
if CSM was not aware of these problems prior to the State takeover, once the
State takeover occurred, it would have been apparent that the county schools had
problems. CSM entered into the collaboration agreement a month after the State
takeover. Thus, to the extent that the problems in the county schools caused
CSM's noncompliance with any requirements, that noncompliance resulted from
CSM's deliberate decision to enter into the collaboration agreement despite the
existence of problems severe enough to require the State takeover, and was not
the result of a factor outside CSM's control. Moreover, CSM does not dispute
ACF's assertion that CSM could have terminated the collaboration agreement if it
became apparent to CSM after entering into the collaboration agreement that the
problems in the county schools would interfere with its ability to comply with
the applicable requirements. 35 In addition, the State takeover occurred more
than eight months before the end of the period for correction under CSM's
approved QIP, yet CSM proffers no evidence that it took any steps at all to
correct its noncompliance in the collaboration classrooms.
Furthermore, even viewing the evidence in
the light most favorable to CSM, the evidence is insufficient to show a nexus
between the July 2001 flood or the May 2002 flood and any of the specific
findings of noncompliance. Ms. Valentine's affidavit alleges that the flooding
in May 2002 "either destroyed or delayed records" for the collaboration
classrooms; however, with the exception of the finding relating to
record-keeping, ACF's findings of noncompliance rely not only on the lack of
records but also on admissions made by teachers in the collaboration classrooms
or other county school personnel who were interviewed by the reviewers. The
allegation that records were destroyed or delayed does not undercut these
admissions. 36 Furthermore, the regulations at 45 C.F.R. §
74.53(b) (made applicable to Head Start grants by 45 C.F.R. § 1301.10(a))
provide that all documents pertinent to a grant award shall be retained for a
period of three years from the date of the submission of the quarterly or annual
financial report, or until "all litigation, claims or audit findings involving
the records have been resolved and final action taken." The Board has
consistently held, with respect to an earlier version of this requirement at
section 74.21(a), that a grantee is not excused from producing relevant
documentation unless it shows that specific documents actually existed, were
retained for the requisite three-year period, and then were innocently
destroyed. See, e.g., California Dept. of Health Services, DAB No. 1240
(1991). (The allegation that records were "delayed" is irrelevant since CSM had
ample opportunity in this proceeding to produce any records not shown to the
reviewers.) CSM never alleged the existence of specific documents prior to the
May 2002 flood that in its view would have established compliance with any of
the performance standards at issue.
Since we have found that CSM presented no
evidence from which a trier of fact could reasonably conclude that the flooding
and State takeover caused its noncompliance, we need not reach the issue of
whether ACF had a legal duty to consider these factors. 37
CSM also argues that in light of the
factors discussed, ACF should have given it a full year from ACF's February 13,
2003 letter to correct any deficiencies. According to CSM, it "proposed longer
time frames," but ACF "insisted on the 180 day time frame in the February 2003 .
. . letter." CSM Appeal Br. at 10-11. Since we have concluded that CSM has not
raised a genuine dispute as to whether its noncompliance was caused by factors
beyond its control, we need not reach this further argument. However, we note
that the Act and implementing regulations give ACF the discretion to determine
the length of the correction period. The only limitation on this discretion is
that ACF not allow more than one year to correct noncompliance pursuant to a
QIP. See 42 U.S.C. § 9836a(d)(2)(A)(ii); 45 C.F.R. § 1304.60(b) and (c). CSM
cites no authority that would require (or permit) the Board to overturn a
termination decision based solely on ACF's choice of a period of less than one
year for correction of deficiencies.
Conclusion
For the reasons discussed above, we grant
ACF's motion for summary affirmance and uphold ACF's termination of CSM's Head
Start grant.
Judge
______________________
Judith A. Ballard
______________________
Cecilia Sparks Ford
______________________
Sheila Ann Hegy
Presiding Board
Member
Footnotes
[1] Subpart B of 45
C.F.R. Part 1304, which is comprised of sections 1304.20 - 1304.24, is captioned
"Early Childhood Development and Health Services." Subpart C of 45 C.F.R. Part
1304, which is comprised of sections 1304.40 - 1304.41, is captioned "Family and
Community Partnerships." Subpart D of 45 C.F.R. Part 1304, which is comprised of
sections 1304.50 - 1304.53, is captioned "Program Design and Management."
[2] Section
641A(d)(1)(B)(ii), which was added to the Act on October 27, 1998, several
months after section 1304.60(b)'s effective date,
gives ACF authority to require correction within 90 days without a QIP. See Pub. L. No. 105-285, § 108(d); 61 Fed. Reg. 57,186
(Nov. 5, 1996).
[3] Compliance
with certain Head Start requirements, e.g., record-keeping, can be established
only through documentary evidence. For those
requirements, a genuine dispute of material fact can exist only when the
position of the party opposing summary judgment is supported by documentary
evidence, absent an allegation that the documentation is not available because
of circumstances beyond the grantee's control. Thus, the absence of
documentation in and of itself may be a basis for summary judgment. Union Township Community Action Organization at 7.
[4] In a related
prior proceeding before the Board (discussed later), CSM asserted that under the
collaboration agreement, the McDowell County Board of Education (BOE) operated
the collaboration classrooms "effectively, as a delegate agency." Docket No.
A-04-142, Motion to Dismiss or Remand dated 8/5/04, at 17. ACF denied that the
BOE was a delegate agency, noting, for example, that the collaboration agreement
had not received prior approval from the responsible HHS official, as 45 C.F.R.
§ 1301.33 requires for creation of delegate agencies. ACF letter dated 10/19/04,
at 1-2. CSM no longer argues that the BOE is a delegate agency and also does not
dispute ACF's assertion that CSM, as grantee, has full responsibility for the
compliance with Head Start requirements of all of its classrooms, including the
collaboration classrooms. If CSM did dispute these legal matters, we would
resolve them in favor of ACF. We see no basis for finding the BOE a delegate
agency and note, in any event, that termination of a Head Start grantee can be
based on the actions of a delegate agency. See Richmond
Community Action Program, Inc., DAB No. 1571, at 35 (1996) (stating that
while Head Start performance requirements apply to both the grantee and its
delegate, "the regulations, taken as a whole, indicate that it is the grantee
who is directly responsible for the operation of the Head Start program and
against whom ACF may take appropriate action.") We also see nothing in the
definition of "collaboration" or "collaborative relationships" in 45 C.F.R. §
1304.3 that indicates that such relationships modify in any way the grantee's
legal responsibility for operating its Head Start program in compliance with
Head Start requirements.
[5] ACF's February
13, 2003 letter identifies the end of this 180-day period as August 26, 2003.
CSM Ex. 5, at 3.
[6] Prior to that
date, CSM submitted at least one QIP that ACF found unacceptable. See ACF Br. dated 1/25/05, at 4-5, citing ACF Exs. 3-5
and 26.
[7] The Board
found principally that the notice did not clearly indicate the factual findings
and authorities on which ACF relied for each of the regulatory bases for
termination other than section 1303.14(b)(4) that were specified in the
termination notice.
[8] CSM concedes
that in its replacement termination notice, "ACF corrected . . . the major flaws
from the July 2004 letter," and, while challenging deficiency determinations,
cites no uncorrected "flaw." CSM Appeal Br. at 6.
[9] The Presiding
Board Member noted that nothing on the face of the document submitted as Exhibit
70 identifies it as a draft report, but provided an opportunity for CSM to
submit information to show that it is a draft report. CSM made no response.
[10] CSM does not
appear to dispute ACF's initial findings in the areas of record-keeping or
ongoing monitoring.
[11] We discuss
ACF's findings of noncompliance in eight of the nine areas addressed in ACF's
motion for summary affirmance. CSM may have raised an issue of material fact
with respect to the finding in the one remaining area (identified by ACF as
"fiscal management") that CSM was not complying with 45 C.F.R. § 74.21(b)(3) at
the time of the initial on-site review. See CSM Ex.
60 (Affidavit of Brenda Melnik, CSM's Finance Director) at 5 (alleging that new
financial management procedures adopted by CSM in July 2002 were implemented no
later than September 2002). We need not reach this issue since a single
uncorrected deficiency is sufficient to warrant termination of funding (45
C.F.R. § 1303.14(b)(4)) and ACF's eight other findings provide a legally
sufficient basis for ACF's termination of CSM's Head Start funding since CSM has
not raised a genuine dispute of material fact regarding them.
[12] CSM argues
that the provision on planning in section 1304.51(a)(1)(iii) requires only
"implementation of the program planning process itself." CSM Appeal Br. at 43.
(Both CSM and ACF erroneously refer to section 1304.20(a)(1)(iii) instead of
1304.51(a)(1)(iii). There is no subsection (iii) in section 1304.20(a)(1).) CSM
asserts that it complied with this requirement since, in addition to having "a
written plan for child outcomes," CSM "has implemented a detailed, on-going
process for program planning, which is reproduced in the program's Annual
Calendar." id., citing CSM Ex. 45. CSM also notes ACF's concession that CSM had
developed a written plan for tracking child outcomes. id. citing CSM Ex. 5, at
8. ACF disputes CSM's reading of the planning requirement, arguing that it
includes a requirement for actual tracking of child outcomes. MSA at 33-34. We
conclude that ACF's reading of the regulation is reasonable in light of the
lead-in language in section 1304.51(a)(1) requiring a grantee to "develop and
implement a systematic, ongoing process of program planning . . . ." Without
actually tracking child outcomes, a grantee would be unable to do ongoing
program planning for Early Childhood Development and Health Services, which
requires individualization based on child outcomes data, because the grantee
would not have the data necessary to evaluate and update its plans. Moreover,
CSM's approved QIP indicates that CSM understood ACF's interpretation, which was
stated in the 2003 Review Report, since the corrective action for this
noncompliance includes analyzing child outcomes data. CSM Ex. 3, at 4.
[13] Section 1306.23(a) provides that "Head Start
grantees must provide pre-service training and in-service training
opportunities" that, among other things, are "directed toward improving the
ability of staff and volunteers to deliver services required by Head Start
regulations and policies."
[14] ACF's motion did not specifically rely on
the other finding in the 2004 Follow-Up Report that there was a lack of adequate
monitoring in the area of fiscal management.
[15] CSM
continued to dispute ACF's interpretation of the requirement for planning as
requiring implementation as well as development of a child outcomes plan. CSM
Response to MSA at 42. Nonetheless, CSM argued that it complied with the
requirement as interpreted by ACF.
[16] Although
we do not describe the contents of these and other exhibits cited by CSM (with
some limited exceptions), we have thoroughly examined each and every one of
them.
[17] Upon further review, it appears that
certain pages in a few of the documents in CSM's exhibits pertain to
collaboration classrooms or teachers; however, these documents are not probative
because they pertain to time periods after the deadline in CSM's approved QIP
for correcting the deficiencies. See, e.g., CSM Ex.
53 (documents showing communication with collaboration classroom teachers
regarding health services). In addition, CSM's 2002-2003 Head Start program
calendar, also submitted by CSM as evidence of compliance with the requirement
for communication, was prepared for distribution to one of the collaboration
classrooms. See CSM Ex. 57. However, there is no evidence of similar
communication with the remaining eight collaboration classrooms.
[18] Although ACF stated that one of the reports
was for the relevant period, the dates on the documents show otherwise. We also
note that the observations discussed in the monitoring reports were made after
the date CSM certified to ACF that it had corrected all deficiencies (September
25, 2003) and, indeed, more than one year after ACF's initial notice of
deficiencies. Thus, even if ACF had given CSM the maximum one-year correction
period ACF is allowed to give under 45 C.F.R. § 1304.60(c), these documents
would be immaterial.
[19] CSM refers to "some of the items listed in
the ACF October 2004 termination letter" when making this argument, implying
that the argument applies to more than one of the findings of noncompliance. CSM
Response to Board Order to Develop the Record at 2. However, the only example
CSM gives pertains to curriculum and assessment.
[20] The
preamble to the 1996 revised Head Start regulations states that "the term
'substantially' [in 45 C.F.R. § 1304.3(a)(6)(i)(C)] does not necessarily mean
that a majority of the requirements are not being met but, rather, that a
knowledgeable person reviewing the findings would determine that the grantee
agency is not operating a quality program." 61 Fed. Reg. 57,185, 57,207 (Nov. 5,
1996). Thus, "substantial performance" is a qualitative, not a quantitative,
assessment.
[21] CSM also argues that it was not given
adequate notice of the alleged fiscal management deficiency because the factual
findings regarding this deficiency in the initial and follow-up reviews were too
dissimilar. We do not need to reach this issue since, as explained earlier, we
do not rely on ACF's findings regarding fiscal management in concluding that
termination was warranted.
[22] CSM indicated that these were only
examples, and did not provide a comprehensive list of all of the respects in
which it believed the letter was unclear.
[23] CSM notes that this language was changed
in the version of the 2003 Review Report that was sent to it with ACF's October
19, 2004 letter. CSM Appeal Br. at 17, comparing CSM Ex. 7, at 10 with CSM Ex.
1, at 10. According to ACF, the version of the 2003 Review Report it sent to CSM
in October 2004 was printed using revised software that merely changed how ACF's
review findings were organized and presented. MSA at 16. In any event, for
purposes of determining whether CSM was given notice and an opportunity to
correct the deficiency, we look to the version of the report that CSM received
with ACF's February 13, 2003 letter.
[24] A copy of this document is not in the
record, but currently appears at
http://www.headstartinfo.org/pdf/PRISMGuide2004.pdf.
[25] Although we would expect ACF to make every
attempt to follow the Guide, the 45-day provision therein is not a regulatory
deadline.
[26] Contrary to what CSM's argument implies,
the period for correction of any deficiencies did not extend to the time of the
follow-up review. (In any event, the follow-up review commenced in November 2003
and was simply continued in March 2004.) Instead, as discussed earlier, CSM was
required by its approved QIP to correct its deficiencies (whatever the relevant
standard for correction) within 180 days of receipt of notice of the
deficiencies (by August 26, 2003).
[27] Here, CSM does not claim that ACF's
February 13, 2003 letter did not provide adequate notice that CSM was required
to fully correct its deficiencies.
[28] Philadelphia
Housing Authority does not refer to the definition of "[m]inimum
requirements" in section 1304.3(a)(14). However, that term, like the definition
of "deficiency," does not describe the level of performance necessary to correct
a deficiency. See section 1304.60(b) (stating that "[i]f the responsible HHS
official, as a result of information obtained from a review of . . . a Head
Start grantee, determines that the grantee has one or more deficiencies, as
defined in §1304.3(a)(6) of this part, and therefore also is in violation of the
minimum requirements as defined in § 1304.3(a)(14) of this part, he or she will
notify the grantee . . . of the finding, identifying the deficiencies to be
corrected . . . .").
[29] Even if the proper standard were
substantial compliance, that would not change the result in this case since CSM
did not raise a genuine dispute of material fact as to whether it was
substantially performing either the requirements related to Early Childhood
Development and Health Services or the requirements related to Program Design
and Management.
[30] We also
question whether a review can fairly be characterized as "perfunctory" based
simply on the quantity or type of information a reviewer is observed to examine
at any given time. The reviewer might have examined other information of which
the observer is unaware or, as the reviewer indicated here, might not need to
examine additional information to make an accurate evaluation.
[31] ACF describes the current review process,
which uses an instrument known as the Program Review Instrument for Systems
Monitoring (PRISM), as an "integrated, comprehensive outcome-focused approach"
that enables ACF "to obtain 'big picture' information about the grantee" such
that ACF is not required to consider other information. ACF Response to Order at
7-8. ACF contrasts this with the On-Site Program Review Instrument (OSPRI) used
to measure the grantee's compliance in the case cited by CSM (discussed below).
The OSPRI, ACF states, was so "detail-oriented," that "monitoring reviews almost
always found specific items that needed to be improved, even in otherwise
excellent programs." id. For this reason, ACF would consider other relevant
information in addition to the OSPRI findings when determining whether a
deficiency existed. id. at 8. This comparison suggests that the scope and
flexibility of the PRISM review process enables CMS to consider as an integral
part of that process information that would only have been considered outside
the process under OSPRI. Moreover, the record shows that, prior to the initial
on-site review, ACF took into account the impact that the flooding had on the
operation of CSM's Head Start program. According to the Head Start program
specialist assigned to CSM, on August 21, 2001, ACF provided CSM with $31,032 in
emergency flood funds and waived $7,758 of non-federal match due to the natural
disaster. ACF Ex. 26, 11. In addition, on November 11, 2002, ACF provided CSM
with $7,755 in reprogrammed funds for flood recovery. id.
[32]The report on the performance audit found
that "[u]nhealthy and unsafe conditions exist in many schools that place
employees and students in danger," that "[n]umerous statutory and policy
requirements are not being followed related to instructional programs,
personnel, finance, and facilities that prevent students from obtaining a
thorough and efficient education," and that "[d]eficiencies exist in leadership
throughout the system." CSM Ex. 72, 9, quoting Att. A.
[33] A previous collaboration agreement with
CSM, signed in the fall of 1999, was cancelled by the county school system on
October 9, 2000. CSM's Response to Order to Develop the Record at 4-5, citing
CSM Ex. 74, 3, 5 and CSM Ex. 72, 3-6.
[34] CSM refers to two floods in addition to
the May 2002 flood, a July 2001 flood (addressed in another affidavit discussed
below) and a November 2003 flood. With respect to the latter flood, CSM alleges
only that the November follow-up review "ended a day early because flooding
forced the evacuation of the review team." CSM Response to MSA at 3.
[35] The collaboration agreement provides that
either party may terminate the agreement by providing a 90-day written notice to
the other party. CSM Ex. 74, Att. E, at 4.
[36] None of the affidavits submitted by CSM
disputes the description in the 2004 Follow-Up Report of what teachers or other
individuals told the reviewers when interviewed.
[37] We note that Home
Education Livelihood Program, DAB No. 1598 (1996)(HELP), on which CSM relies, is factually and legally
distinguishable. HELP served children of migrant farm workers, and the Board
found a reasonable nexus between the grantee's inability to predict crop
conditions and its inability to maintain full funded enrollment when crop
conditions were poor. The Board also factored in ACF's failure to fund HELP
until more than three months into its program year. As discussed below, CSM has
not presented any evidence of a nexus between the flooding and State takeover
and any specific deficiency findings. Neither was there a funding delay here; in
fact, as noted earlier, ACF gave CSM additional funding because of the floods.
Legally, while the Board reversed ACF's termination of HELP based, in part, on
factors it concluded were beyond the grantee's control, it did not hold that ACF
must always consider factors claimed to be beyond a grantee's control. Also, as
CSM acknowledges, the Board decided HELP under
earlier Head Start regulations. Those regulations required ACF to make an
independent determination that a deficiency was material in order to terminate
based on that deficiency, while the present regulations presume that a
deficiency is material. Thus, there was a question in HELP that is not present here as to whether any "unique
factors" cited by the grantee would render its noncompliance immaterial.

|