A grantee which purchases a modular
unit with grant funds or receives approval of a continuing purchase must have
the modular unit inspected by a licensed engineer or architect within 15
calendar days of its installation or approval of a continuing purchase, and must
submit to the responsible HHS official the engineer's or architect's inspection
report within 30 calendar days of the inspection.
[68 FR 23223, May 1, 2003]